Henley Construction Company has reported that they have:
- Pepco set transformer and continues permanent power installation
- Poured Stair #1
- Continued spray fireproofing
- Continued with air barrier, all areas
- Continued fiber cement cladding
- Started exterior standing seam wall panels
- Continued with standing seam metal roof
- Continued with curtain wall/storefront frame/glass installation
- Completed stone veneer at retaining wall
- Continued with interior/exterior stone veneer and split face cmu
- Continued pluming rough in, all areas
- Continued electric rough in, all areas
- Continued duct work installation, all areas
- Measured interior storefront frames/began fabrication
- Continued sprinkler mains and branches, all areas
- Started hanging drywall first and second floors, north end
- Started building elevator shaft on stair one walls
- Continued roofing deficiency repairs, per Gale reports